Q4 2026  |  Develop, Sell or Hold · Part 3 of 4  |  Solar & Storage

Big on Megawatts, Light on Value: How to Judge a Development Pipeline

Most capacity that enters a development pipeline never gets built. Why headline gigawatts overstate value, the six markers that separate a high-quality pipeline from a large one, and how far a pipeline shrinks when weighted by stage.

Odette CapitalOctober 20268 min read
13%Share of 2000–2020 U.S. queued capacity that reached commercial operationBerkeley Lab, Jul 2026
41%Share of capacity with a signed interconnection agreement that still withdrewBerkeley Lab, Jul 2026
61Median months from interconnection request to operation, projects built in 2025Berkeley Lab, Jul 2026
26%Share of today’s active U.S. queue with a draft or executed interconnection agreementBerkeley Lab, Jul 2026

Developers report their pipelines in gigawatts, and the numbers are large. Buyers, lenders and investors increasingly discount them. The reason is base rates: most capacity that enters a pipeline never gets built, and the share that does depends on a handful of milestones that a headline megawatt figure does not show.

A development pipeline is a portfolio of options, and most options expire worthless. Its value lies in the megawatts that have already cleared the hurdles that kill projects, not in the megawatts on the list.

Part 2 of this series showed buyers paying full prices for operating and contracted assets and very little for development optionality. This part explains why, sets out the markers that separate a high-quality pipeline from a large one, and shows how quickly a headline number shrinks once it is weighted by stage.

The base rates are poor

Berkeley Lab’s Queued Up 2026 is the most complete record of what happens to U.S. projects after they request a grid connection. Of the capacity that requested interconnection between 2000 and 2020, only about 13% had reached commercial operation by the end of 2025, and about three-quarters had withdrawn. Even a signed interconnection agreement is no guarantee: of the capacity that signed one between 2000 and 2022, 43% was operating, 41% had withdrawn and 15% was still active.

What happens to queued U.S. capacity

Status at end-2025, share of capacity

All requests, 2000–2020 13% ~75% withdrawn Signed interconnection agreements, 2000–2022 43% operating 41% withdrawn 15%
OperatingWithdrawnStill active
Source: Lawrence Berkeley National Laboratory, Queued Up 2026, July 2026. The “still active” share of the 2000–2020 cohort is the remainder after operating and withdrawn capacity.

Today’s queue is no more mature. Only 26% of the 2,061 GW of active U.S. requests, about 536 GW, had a draft or executed interconnection agreement at the end of 2025. And the wait has lengthened: the median project built in 2025 took 61 months from interconnection request to commercial operation, against under two years for projects built in 2004–08.

Completion rates differ by market

Share of 2000–2020 interconnection requests that reached commercial operation

ERCOT24% ISO-NE18% Non-ISO West10% CAISO8%
Source: Berkeley Lab, Queued Up 2026. ERCOT is the only region where more than 20% of requested capacity reached operation. Selected regions shown.

European queues are, if anything, more speculative, as Part 1 showed. Italy’s grid operator held 268 GW of standalone storage requests in March 2026. German transmission operators held 211 GW of battery requests against 41 GW of storage needed by 2037. Poland’s queue exceeds 240 GW against 33 GW in operation. In the UK, connections reform took a 722 GW queue and gave priority status to 283 GW. In Europe, a firm grid connection is the single most important filter on pipeline value.

Six markers of a high-quality pipeline

MarkerWhat good looks likeRed flag
Grid connectionSigned interconnection agreement or firm connection offer, with a known energisation date and upgrade costsQueue position only; non-firm access; network upgrade costs not yet allocated
Site & permitsLand under lease or ownership; permits in hand, or a route that avoids federal reviewLand options only; a federal nexus that routes the project through Interior review
OfftakePPA, toll or capacity contract with a creditworthy counterpartyMerchant exposure in saturating markets, such as ERCOT ancillary services or German aFRR
Tax & trade (U.S.)Documented begin-construction position and continuity plan; supply chain that meets FEOC thresholdsSolar with no begin-construction position after July 4, 2026; storage with unverified FEOC exposure
FinancingConstruction debt and tax equity or credit transfer committedNo lender engagement; reliance on merchant revenue to size debt
Conversion recordDisclosed history of pipeline converting to COD and sale prices achievedLate-stage book shrinking while total megawatts grow; repeated impairments of early-stage projects

Weighting the pipeline by stage

The simplest test of a pipeline is to weight each stage by its chance of reaching operation. The example below applies Berkeley Lab’s base rates to a hypothetical 10 GW pipeline with the stage mix typical of large developers today, in which most capacity is early stage.

A 10 GW pipeline, weighted by stage

Illustrative, GW

Headline Early stage 7.0 1.5 1.5 Risk-weighted: about 2.9 GW 0.9 early + 0.6 advanced + 1.35 late stage ≈ 29% of headline
Early stage × 13%Advanced, with interconnection agreement × 43%Backlog and under construction × 90%
Illustrative only. The 13% and 43% conversion rates are Berkeley Lab historical base rates for all U.S. requests and for signed interconnection agreements. The 90% rate for contracted and under-construction projects is an Odette assumption. Actual rates vary by market, technology and developer.

On those assumptions, a 10 GW pipeline is worth about 2.9 GW of expected capacity, and almost half of that comes from the 15% of the pipeline that is already late stage. Two pipelines with the same headline can differ several-fold in expected capacity, and more in value, because late-stage megawatts also carry less remaining development spend.

What a weakening pipeline looks like

The markers above are visible in public disclosures. One large listed developer’s reports over the 18 months to mid-2026 show the pattern a buyer should look for:

IndicatorWhat the disclosures show
Late-stage bookSolar under construction and in backlog fell about 36%; storage fell about 49%
Early-stage bookEarly-stage storage rose about 23%; early stage is now over 70% of solar and over 80% of storage megawatts
Grid rightsSecured interconnection covers under a third of the solar pipeline and about a sixth of the storage pipeline; secured solar interconnection has roughly halved since 2023
Write-downsImpairments of early-stage projects, which management linked partly to sharply higher interconnection costs, and exits from early-stage development in several markets
SalesProject sales delayed by permitting; per-project sale prices not disclosed

None of this means the pipeline has no value. It means the headline total overstates it, and that the trend matters as much as the level: a pipeline whose late-stage share is falling is being consumed faster than it is being replenished with quality projects.

What the market pays for quality

Transaction prices show the gap between de-risked and speculative megawatts. In July 2026, EDP Renováveis sold 80% of a 384 MW California solar and storage portfolio, contracted under a 20-year PPA and a 20-year toll, at an enterprise value of about $0.8 billion for 100%, roughly $2.1m per MW, and a projected gain of about 40% over invested capital. At the other end, the average Spanish ready-to-build solar project traded at about €38,000 per MWp in early 2026.

Platforms can still command premiums when the pipeline has a differentiated route to market. Alphabet paid $4.75 billion for Intersect’s development platform, which co-locates generation with data-centre load, while leaving its existing operating assets with their prior owners. What it bought was a pipeline with a buyer for the power already in mind.

How to diligence a pipeline

Questions to ask

  • How much capacity holds a signed interconnection agreement or firm connection offer, and on what dates?
  • What share of late-stage capacity is contracted, and with whom?
  • How has the late-stage book moved over the last six quarters, net of sales?
  • Which projects carry a federal nexus or unresolved FEOC exposure?

Data to request

  • Project-by-project stage, interconnection status and upgrade cost estimates.
  • Historical conversion from each stage to COD or sale, by market.
  • Remaining development spend to reach notice to proceed, by project.
  • Prior sale prices and the counterparties that paid them.

Bottom line. A high-quality pipeline is one in which a meaningful share of capacity has a grid connection, permits, an offtaker, a tax and trade position and financing. Weighted by stage, most headline pipelines are worth a fraction of their gigawatts. Part 4 asks what happens when a developer keeps those projects instead of selling them.

Data as of October 15, 2026. The weighted-pipeline example is illustrative, and the developer case is drawn from public company filings and presented without naming the company. This piece is for informational purposes only and does not constitute investment advice.

Sources
  1. Lawrence Berkeley National Laboratory, Queued Up 2026 release, July 1, 2026. Link
  2. Lawrence Berkeley National Laboratory, Queued Up 2026 slide deck (interconnection agreement outcomes, completion rates by region, time to COD). Link
  3. pv magazine on Terna’s queue, Apr 16, 2026. Link
  4. Modo Energy on German battery grid access, Apr 9, 2026. Link
  5. Modo Energy on Poland’s grid queue, Apr 4, 2026. Link
  6. Knight Frank on UK connections reform, Dec 11, 2025. Link
  7. Public company filings (SEC Form 6-K quarterly results, December 2024 to June 2026, and earnings calls) for the developer case.
  8. EDPR market notification on its 384 MW California solar and storage rotation, July 27, 2026. Link
  9. ION Analytics/Infralogic on Spanish project prices, June 4, 2026. Link
  10. Cleary Gottlieb on Alphabet’s acquisition of Intersect, Mar 2026; TechCrunch, Dec 22, 2025. Link · Link

Need an independent view of a pipeline?

Odette advises developers and investors on pipeline valuation, sell-side positioning and buy-side diligence for solar, storage and wind.

Engage Now

More from Research & Insights

Battery Storage

BESS Duration Economics: When 2-Hour vs. 4-Hour Storage Is More Accretive

Why the value-maximizing battery duration differs from one U.S. power market to the next.

Read the analysis →
Battery Storage

From Queue to COD: Building a Utility-Scale Battery Storage Plant

Development and construction timelines for a 100 MW battery storage project, from queue entry through commercial operation.

Read the analysis →
Power Markets

Strategies for Success in CAISO: The IRA Era

How California’s wholesale power market rewards solar and storage after the Inflation Reduction Act.

Explore the research →